Monthly Archives: March 2015
Steg (Tunisia)
Project: Supply, Fabrication and Erection of 1800 Tons of steel Structure for Turbine buildings and auxiliary , 09 surges vessels and air intake system for Sousse D Power Plant
Main contractor: Ansaldo Energia
Owner: Steg (Tunisia)
Year: 2013 / 2014
LISCO -Libyan Iron & Steel Company- (Libya)
Project: Engineering, Fabrication and Construction of new STACKER (4000T/hour) and RECLAIMER (1000T/hour) machines and expansion of the present pellet stock yard
Main contractor: Socomenin
Owner: LISCO -Libyan Iron & Steel Company- (Libya)
Year: 2009/2010
LISCO -Libyan Iron & Steel Company- (Libya)
Project: Design, Supply, and Erection of exchangers with all underground piping for new cooling unit (Pipes Ø1600, 90 and 70 m)
Main contractor: SOCOMENIN
Owner: LISCO -Libyan Iron & Steel Company- (Libya)
Year: 1995
Sapetro (Benin)
Project: Supply and Fabrication of an offshore subsea structure elements of a conduc- tor supported platform (CSP) project.
Dimensions : H 14,3 m, L 6,5 m, W 5,5 m (Weight : 120T)
Main contractor: Aquaterra Energy (UK)
Owner: Sapetro (Benin)
Year: 2013-2014
GCT Group Chimique Tunisien (Tunisia)
Project: Supply, fabrication and Installation of steel process equipment for new phosphoric acid plant at Mdhilla II – Tunisia on EPC basis
Main contractor: Socomenin / Hyundai Eng / SBF
Owner: GCT Group Chimique Tunisien (Tunisia)
Year: 2010 – 2015
Sapetro
Project: Supply and Fabrication of an offshore topside structure elements of a conductor supported platform (CSP) project.
Dimensions: H 15 m, L 12 m, W 6 m (Weight: 200T with Equipments)
Main contractor: Aquaterra Energy (UK)
Owner: Sapetro (Benin)
Year: 2013-2014
ACUAMED -Sociedad Estatal Aguas de las Cuencas Mediterráneas- (Spain)
Project: Design, Supply, Fabrication and Delivery of 10 Sand filter for Almanzora desali- nation plant (Diam: 3,8 m; length: 20 m).
Main contractor: Befesa
Owner: ACUAMED -Sociedad Estatal Aguas de las Cuencas Mediterráneas- (Spain)
Year: 2008
Serept (Tunisia)
Project: EPC contract for Z5105 skid mounted stabilization package (decanter, Re-boiler (Heat exchanger) and column for the Ashtart revemping project.
Main contractor: Socomenin
Owner: Serept (Tunisia)
Year: 2011
Carthage cement (Tunisia)
Project: Mechanical and steel erection works of rotary kiln and raw mill at Carthage Cement Plant (Djebel Ressas)
Main contractor: Ekon
Owner: Carthage cement (Tunisia)
Year: 2011 – 2012
IET
ENGINEERING
www.iet-engineering.com
GCT Group Chimique Tunisien (Tunisia)
Project: Supply, Fabrication and Delivery and Erection of convertor, towers and stack for new sulfuric acid plant at Mdhila II – Tunisia
Main contractor: ECEC
Owner: GCT Group Chimique Tunisien (Tunisia)
Year: 2012/2014
Tifert -Tunisian Indian Fertilizers Company- (Tunisia)
Project: Supply, Fabrication and Installation of steel Process equipment for phosphoric acid plant (360 000T/Year P2O5) in Skhira-Tunisia (49 vessels for concentration unit (850 T) and 18 vessels for diluted acid unit (200T)
Main contractor: Socomenin / Wec (JV)
Owner: Tifert -Tunisian Indian Fertilizers Company- (Tunisia)
Year: 2008/2010
AEC -Algerian Energy Company- (Algeria)
Project: Design, Supply, Fabrication and Delivery of 108 Anthracites & Sand filters for Skikda, BENI SAF and Honaine desalination plant (135m3; Length: 13000 mm;
Main contractor: GEIDA-UTE
Owner: AEC -Algerian Energy Company- (Algeria)
Year: 2006/2007/2008
Gmmra (MMRA – Libya)
Project: Supply, Fabrication and Delivery of 24 HP surge vessels 250 m3 for Wadi Tumellah surge area
Main contractor: VINCI Construction
Owner: Gmmra (MMRA – Libya)
Year: 2006-2007
Ministry of Electricity & Water (Kuwait)
Project: Design, Supply and Fabrication of 10 surge vessels (120 m 3 ) for Mina Abdullah WDC II
Main contractor: ABB AG Power System Division
Owner: Ministry of Electricity & Water (Kuwait)
Year: 2013
GMRWUA (MRWUA – Libya)
Project: Supply, Fabrication and Delivery of 15 surge vessels (250 m3), manifolds, fittings and complete mechanical installation of AG and GAG pumping stations at Sirt
Main contractor: ABB Utilities-Metis
Owner: GMRWUA (MRWUA – Libya)
Year: 2006/2007
GMMRA (MMRA – Libya)
Project: Design, Supply, Fabrication and Site Erection of steel pipes and fittings equip- ment for The KUFRA Conveyance line (flow control/regulating stations) 2 000 T.
Main contractor: Tekfen – TML – JV
Owner: GMMRA (MMRA – Libya)
Year: 2008/2010
GMMRA (MMRA – Libya)
Project: Supply and fabrication of 32 special fittings (Diam:40m; length:7,5m) for the twin SARIR to ADJDABIA conveyances
Main contractor: AL NAHER CO.LTD pipe manufacturing
Owner: GMMRA (MMRA – Libya)
Year: 2004
GMMRA: (MMRA – Libya)
Project: Supply, Fabrication, Delivery of steel manifold, piping spools, special fittings, surge vessels, miscellaneous steel works and mechanical installation of pumping stations PS1 & PS2 (TAZ project)
Main contractor: Metis
Owner GMMRA: (MMRA – Libya)
Year: 2006-2007
GMMRA (MMRA – Libya)
Project: Supply, Fabrication and Delivery of 165 tank filters 50 m3 and 54 backwash tanks 70m3 along with 1400 T of galvanized supporting steel structures.
Main contractor: Idreco S.p.a
Owner: GMMRA (MMRA – Libya)
Year: 2002
GAMRWUA (AMRWUA – Libya)
Project: Design, Supply, Fabrication & Erection of 10 Surge pressure Vessels, steel pipe spools and fitting for booster pump stations for Rejma Ghut Essoltan and Benghazi Plain project.
Main contractor: Kolin
Owner: GAMRWUA (AMRWUA – Libya)
Year: 2010 / 2011
Agence Nationale des Barrages et Transferts « ANBT » (Algeria)
Project: Design, Supply and Fabrication of 20 surge vessels for Setif–Hodna pumping stations.
Main contractor: Mapa Construction And Trading CO. INC.
Owner: Agence Nationale des Barrages et Transferts « ANBT » (Algeria)
Year: 2011
Agence Nationale des Barrages et Transferts « ANBT » (Algeria)
Project: Design, Supply and Fabrication of 8 surge vessels: 2 SV 90 m3 – 40 Bar // 3 SV 250 m3 – 25 Bar // 3 SV 225 m3 – 25 bar for MAO project.
Main contractor: ABB AG Power System Division
Owner: Agence Nationale des Barrages et Transferts « ANBT » (Algeria)
Year: 2009
Abdul Latif Jameel
Project: Supply and Fabrication of The tallest flagpole in the world (H:170 m, Diam from 2,3 m to 4 m) located at Jeddah, KSA
Main contractor: Al Babtain-Le Blanc
Owner: Abdul Latif Jameel
Year: 2013 / 2014
Ethiopia
Project: Supply, Fabrication and packing of 30 wind towers 65m 1MW
Main contractor: Vergnet
Destination: Ethiopia
Year: 2010
Tunisia
Project: Fabrication of 128 wind towers AE61 55m (1,3MW)
Main contractor: Made – Gamesa
Destination: Tunisia
Year: 2010 -2011
Europe
Project: Supply and Fabrication of 98 wind towers LTW77 H 65, 34 wind towers LTW80 HH80 and 16 main frame for Nacelle
Main contractor: Leitner Leitwind
Destination: Europe
Year: 2007 / 2014
Steg (Tunisia)
Project: Design, Supply, Fabrication and Erection of 7 fuel oil and water storage tanks ((2*3000 / 2*2000 / 2*500 / 1*100) m 3) for Ghannouch power plant
Main contractor: Alstom Power
Owner: Steg (Tunisia)
Year: 2009/2010
Sonelgaz (Algeria)
Project: Supply of 19 shop fabricated Tanks ASME stamped for Hadjret Ennous power plant (1200MW)
Main contractor: Snc Lavalin
Owner: Sonelgaz (Algeria)
Year: 2007
Sonelgaz (Algeria)
Project: Design, Supply, Fabrication of: 2 fuel oil storage tanks (10 000 m3), 1 fire water storage tank (1800 m3) and Raw water storage tank (500 m3) For Berrouaghia power Plant
Main contractor: Saipem
Owner: Sonelgaz (Algeria)
Year: 2006
Gecol (Libya)
Project: Detailed design, Fabrication and Erection of steel structures for EZZAWYA gas turbine buildings (1200T)
Main contractor: Bilfinger & Berger
Owner: Gecol (Libya)
Year: 1998
Steg (Tunisia)
Project: Supply, Fabrication and Delivery of Chimney for “la Goulette” power station.
Main contractor: GE International Inc
Owner: Steg (Tunisia)
Year: 2004
Gecol (Libya)
Project: Prefabrication, Erection, Welding and Painting of 3150 Tons steel structure at Western Mountain Gas turbine power plant project at Ruwais.
Main contractor: Msec
Owner: Gecol (Libya)
Year: 2004/2005 – 2009/2010
J/V Metka S.A – Terna S.A
Project: Supply, Fabrication and Delivery of 16 pressure vessel for Megalopolis CCPP –unit 5
Main contractor: Idreco S.P.A
Owner: J/V Metka S.A – Terna S.A
Year: 2012
Harouge Oil Operations (Libya)
Project: Demolition using water-jet & cold-cutting tools of existing and reconstruction of new 500,000 USBBL Crude Oil Floating Roof Storage Tank ( Diam:80 m / H:17m)
Main contractor: Socomenin
Owner: Harouge Oil Operations (Libya)
Year: 2012-2015
Eni Gas (Libya)
Project: Supply, Prefabrication and Delivery of Tubular Pipe racks for marin jetty at Wafa Costal plant (72 modules, 30T each, 2,1 Km length)
Main contractor: JTS Consortium (JGC / Technimont / Sofregaz) / Contractor: BESIX
Owner: Eni Gas (Libya)
Year: 2003
British Gas (Tunisia)
Project: Engineering, Fabrication and Supply of 18 Pressure Vessels ASME Stamped for Hasdrubal Gas Treatment Project.
Main contractor: Petrofac International LLC (UAE)
Owner: British Gas (Tunisia)
Year: 2007/2008
Total (Libya)
Project: Prefabrication works and erection of a complete unit of gas oil separator (G.O. S.P.) 15000 B / Day At EL-MABRUK, and erection of 5 oil storage tank (5000 BBLS)
Main contractor: GEO Services
Owner: Total (Libya)
Year: 1995
Brega Petrolium Marketing co. (Libya)
Project: Revamping of marin jetty and 28th March terminal in tobruk.
Main contractor: Socomenin
Owner: Brega Petrolium Marketing co. (Libya)
Year: 1994-1996
Perenco (Congo)
Project: Supply and Fabrication of Steel Structure & one Separator Vessel
Main contractor: MG Group
Owner: Perenco (Congo)
Year: 2013
Gulf Oil Company (Libya)
Project: Design, Supply and Fabrication of 6 separators and one degassing boot
Main contractor: Peerless Europe
Owner: Gulf Oil Company (Libya)
Year: 2008/2009
Serept (Tunisia)
Project: Design, Supply, Fabrication and Commissioning of a production separator package Z5103
Main contractor: Socomenin
Owner: Serept (Tunisia)
Year: 2010
Socomenin
EQUIPMENT MANUFACTURING AND INDUSTRIAL CONSTRUCTION
www.socomenin.com.tn
Socomenin industrial construction
INDUSTRIAL CONSTRUCTION
www.sic.com.tn
Socomenin BTP
Civil work
IFAT
Training and qualifying employees in different industrial disciplines.
Sopami
Technical Assistance & Services Compagny
GTT
Global Tunisian Trading
Sosem
EQUIPMENT HANDLING
www.sosem.com.tn
Wind towers
SOCOMENIN Wind Towers Division is specialized in the fabrication of tubular steel towers for the wind energy industry.
In our plant dedicated to serial production of wind towers, we can produce 12000 t/year of wind towers and this up to 6000 mm in diameter with high accuracy geometric tolerances.
Towers are delivered as a package surface treated including assembly of internals.
Construction
Since its creation, SOCOMENIN was involved in large projects in North Africa. Its high level of expertise and project management and construction capabilities, combined with a responsive organizational structure and a policy of forging partnerships with local and international companies, has enabled SOCOMENIN to provide solutions that are both global and modular to meet the wideranging needs of customers, from project management to the provision of turnkey projects.
SOCOMENIN has a large experience in project construction in different field of activities from engineering to commissioning and start up.
Our main construction projects include:
- Storage tanks
– Oil and Gas processing plants
– Separation Units
– Power Generation Plants
– Pumping stations
– Desalination Units
– Chemical processing plants
– Fertilizer plants
– Cement Factories
– Iron and steel plants
– Food Factories
Engineering
Engineering
SOCOMENIN offers Engineering and design services related to EPC Projects and Process equipment manufacturing covering:
- Basic Engineering: Mechanical , Electrical, Civil Engineering works…
- Detailed engineering : Structural, Instrumentation, Mechanical, Piping layout…
SOCOMENIN is using CAD/CAE Design software packages that enable delivering high quality designs to customers.
Design tools
Drawings | AutoCAD / SP3D / Solidworks Pressure vessel Design |
Software | PV ELITE Atmospheric Storage Tank Design: AME Tank |
Steady State and transient Hydraulic analysis | WANDA Piping |
Flexibility analysis and stress calculation | CAESAR II |
Steel Structure and concrete steel Design Software | ROBO BAT |
Steel Structure Detailed Design | X-STEEL |
Finite Element Analysis | COSMOSWORKS/COSMOSM |
Socomenin wind
Storage tanks
Covered area | 2000 m² |
Production capacity | 6000 T/Year |
Lifting capacity | 20 T |
Height under hook | 7 m |
Rolling Capacity | 45 mm |
Equipments List:
– CNC Plasma cutting machine
– Rolling Machine
– Bevelling Machine
– Punching Machine
– Sawing Machine
Structural steelwork
SOCOMENIN Structural steelwork plant is equipped with CNC drilling, cutting and marking unit with a capacity Up to 1 OOOmm in width and with a total capa city of production up to 8000T I Year.
SOCOMENIN is fully compliant with International Standards and specifications such as:
- AISC codes and standards
– AWS D1. 1/ D1.5
– DTU
– NORSOK M101
– EEMUA 158
– EEMUA 197
Surface treatement
In order to keep-up to date with the new technologies, and to improve its products quality, SOCOMENIN Company has established three new blasting shops using metallic girt with 300 000 m²/year capacity.
The three blasting shops are built according to international standard specifications for on-shore and off-shore use, and respecting the specific conditions of both humidity which could be controlled and salinity that could be fixed down to 3µg/cm².
The painting activity is done in 6 conditioned buildings according to the international standards and paint manufacturer’s specifi- cations for onshore and offshore use. Specific conditions, such as humidity and temperature are closely controlled.
These buildings are equipped with air heater generators used in the winter.
RUBBER LINING ACTIVITY
SOCOMENIN have successfully protected such equipment by rubber lining as Filters for water treatment unit, chemical processing and storage tank. Rubber lining is used to protect metal surfaces from corrosion fluid. Like in piping handling Sea Water or chemical product.
Logistics
Storage
From the raw material arrival to the delivery of finished product, SOCOMENIN ensures the required logistical operations.
With more than 10 000 m² of raw material storage area equipped with 03 gantries cranes and with more than 45 000 m² of finished product storage area located close to the SFAX harbor.
SOCOMENIN is able to ensure the storage of all our customers project-related goods.
Export logistics Packing, loading and delivery
In order to meet the European standards, we have operated as per ISPM 15 standards for any packing operation
SOCOMENIN ensures the transportation of goods either by conventional and non conventional sea shipment or by land using special low-bed and standard trucks.